225 kV transmission infrastructure in Sierra LeoneIlustrativo
Comércio de Energia e Crescimento IndustrialAFCEN-WAIIS-ENERGY-SL-006

Northern Corridor Transmission Line (225 kV)

Sierra Leone · Multi-regionEnergy · High-voltage transmission (225 kV)

A 225 kV northern transmission corridor, a national priority project with feasibility completed, that links to the CLSG regional line and ends at a new Newton substation, relieving the single 161 kV feed to Freetown. USD 100m sought as blended equity and debt.

Custo do projeto
c. USD 400m
Estimado, indicativo
Capacidade
225 kV
Capital pretendido
USD 100m
Blended capital sought
Instrumento
Financiamento misto
Blended equity and debt, alongside initial funds already secured.¹
Calendário
To financial close
Then construction

Justificação

About 140 MW of grid supply meets unconstrained demand of about 320 MW, projected at 485 MW by 2030, and a single 161 kV line carries Bumbuna hydro and imports to Freetown.² The corridor relieves that bottleneck and closes a 225 kV ring joined to the CLSG regional line.

Line
225 kV overhead, with optical ground wire
Route
Northern region to a new Newton substation
Link
Joins the 1,303 km CLSG 225 kV line³
Stage
Feasibility completed; in structuring

Oportunidade de investimento

Estrutura da transação

Blended equity and debt for a 225 kV line under a 25-year utility contract, now in negotiation.

Utilização dos fundos

A 225 kV line across the Northern region to a new substation at Newton, with optical ground wire.

Base de receitas

Transmission contract with EDSA, the national distribution utility, as offtaker; 25-year tenor in negotiation.

O pedido

USD 100m in blended equity and debt, alongside the initial funds already secured, to build the corridor.

Porque é financiável

National priority.

Among the priority projects of Sierra Leone's Mission 300 Energy Compact, with feasibility completed and initial funds secured.²

Closes the grid ring.

With the MCC-funded southern corridor, it joins the CLSG 225 kV line and ends at Newton, forming a national ring.²

Removes a bottleneck.

One single-circuit 161 kV line carries Bumbuna hydro and imports to Freetown and limits use of the CLSG interconnector.²

Demand outruns supply.

About 140 MW of grid supply meets demand of about 320 MW, projected at 485 MW by 2030; mining is the largest growth load.²

Dados e evidências · Sierra Leone grid: today and the 2030 plan

Today (2025)With the northern and southern corridors
Main feed to FreetownOne single-circuit 161 kV line225 kV ring joined to the CLSG line
Transmission network802 km1,235 km by 2030
Electricity access36% of the population78% target by 2030

Maturidade e calendário do projeto

  1. OriginationGreenfield
  2. FeasibilityCompleted
  3. StructuringCurrent stage
  4. Financial closePost-diligence
  5. ConstructionTo follow

Principais riscos e medidas de mitigação

Offtake

The 25-year utility contract is still in negotiation; the offtake term sheet is released under NDA.

Utility credit

Revenue depends on the national distribution utility; mining load and lower-cost supply strengthen its revenue base.²

Environmental and social

Category A on AfCEN screening; E&S impact documentation is released in the Tier 2 data room.

Condições da transação

Offtaker
Utility: EDSA, the national distribution utility
Contract status
In negotiation; 25-year tenor
Instrument sought
Blended: equity and debt
Technology
225 kV overhead transmission line with optical ground wire
Location
Northern Sierra Leone to Newton, Western Area; route under NDA
Development stage
Feasibility completed; in structuring
E&S category
Category A (AfCEN screening)
WAIIS pillar
Energy Trade & Industrial Growth

Impacto no desenvolvimento

Access

Supports the national goal of raising electricity access from 36% to 78% of the population by 2030.²

Lower cost

Evacuates lower-cost hydro and imports; the Compact expects supply costs to fall to USD 14–16 cents/kWh.²

Mining and industry

Reliable, low-emission grid power for mining, the largest growth load.²

Integration

CLSG imports are estimated to replace about 80% of the thermal generation Sierra Leone would otherwise need.⁴

  1. Indicative; capital structure under review, final figures released under NDA.
  2. Government of Sierra Leone, National Energy Compact (Mission 300), 2025.
  3. World Bank, Powering Africa results brief, February 2025.
  4. World Bank, CLSG (WAPP APL4) Implementation Completion and Results Report, June 2024.
  5. As imagens são ilustrativas.

O registo cria uma conta de investidor. A AfCEN conclui a integração e o KYC antes de divulgar qualquer coisa além desta página — o PDF do teaser contém exatamente o que está neste ecrã e nada mais.

Apenas indicativo; não constitui uma oferta, um convite ao investimento nem aconselhamento de investimento. Os valores exatos, a identidade do promotor e os documentos do projeto são divulgados a investidores qualificados após a integração e o KYC da AfCEN, ao abrigo de NDA.