Submarine cable landing infrastructure on the Sierra Leone coast.Illustratif
Transformation numériqueSL-SUB-CABLE-02

Sierra Leone Second Submarine Cable

Sierra Leone · Western AreaInformation and Communications Technology (ICT) · Digital Infrastructure / Submarine Telecommunications Cable

A new submarine fibre optic cable project in Sierra Leone aimed at meeting fast-rising international bandwidth demand and lowering wholesale capacity costs. The project targets anchor capacity contracts before financial close and seeks equity alongside committed capital.

Coût du projet
c. USD 38m
Estimated total project cost
Capacité
500 Gbps (forecast demand by 2030)
95.5 Gbps (current operator capacity demand)/an (modélisation)
Capital recherché
USD 25m
Equity sought
Instrument
Fonds propres
USD 25 million equity sought alongside USD 13 million already committed.
Calendrier
To financial close
Anchor contracts in progress

Justification

Sierra Leone’s operators currently buy 95.5 Gbps of capacity at USD 8-15/Mbps/month, with demand forecast to grow 40% a year to 2030 and exceed 500 Gbps. A new submarine cable would add scalable international connectivity to serve this gap.

Asset
Submarine fibre optic cable
Demand
500 Gbps by 2030
Tariff
USD 5/Mbps/month launch
Stage
Late-stage development

Opportunité d'investissement

Structure de l'opération

Equity investment in a submarine cable project with anchor capacity contracts under negotiation before financial close.

Utilisation des fonds

Cable system development, landing infrastructure, network equipment and associated project delivery costs.

Source des revenus

Revenue is expected from wholesale international capacity sales to private operators. Anchor capacity contracts of 3-5 years are under negotiation at launch pricing of USD 5/Mbps/month.

Ce qui est recherché

Equity partners to provide USD 25 million alongside USD 13 million already committed.

Pourquoi le projet est bancable

Unmet demand.

Operators currently purchase 95.5 Gbps and demand is forecast to exceed 500 Gbps by 2030.

Price position.

Launch pricing is set at USD 5/Mbps/month against current market purchases at USD 8-15/Mbps/month.

Advanced preparation.

A 2025 feasibility study supports the project and the financial model has been third-party reviewed.

Site readiness.

A landing site has been selected and grid power is available at the landing location.

Données et éléments probants · Demand and pricing evidence

95.5 Gbps
Current operator demand
40% yr
Demand growth to 2030
500 Gbps
Forecast demand by 2030
8-15 USD/Mbps/mo
Current market purchases
5 USD/Mbps/mo
IPLC launch price

Degré de maturité et calendrier du projet

  1. OriginationGreenfield concept defined
  2. Feasibility2025 study completed
  3. StructuringCurrent stage
  4. Financial closeAnchor contracts pending
  5. ConstructionTo follow

Principaux risques et mesures d'atténuation

Contracting risk

anchor capacity contracts are under negotiation before financial close.

Demand risk

current operator demand and forecast growth underpin the market case.

Delivery risk

feasibility work is completed and the financial model has been third-party reviewed.

Conditions de l'opération

Instrument
Equity
Capital sought
USD 25 million
Committed capital
USD 13 million
Contract tenor
3-5 years for anchor capacity contracts

Impact sur le développement

Digital access

adds international bandwidth capacity for Sierra Leone’s telecom market.

Cost of service

targets lower wholesale capacity pricing than current operator purchases.

Economic activity

supports digital services that depend on resilient international connectivity.

Infrastructure resilience

submarine cables carry more than 99 per cent of global data traffic worldwide.¹

  1. International Telecommunication Union, 2026, https://www.itu.int/en/mediacentre/Pages/PR-2026-07-10-Submarine-cable-resilience-report.aspx
  2. Images à titre d'illustration.

L'inscription crée un compte investisseur. AfCEN finalise le parcours d'intégration et le KYC avant de communiquer toute information au-delà de cette page. Le teaser PDF reprend exactement le contenu de cet écran, et rien de plus.

À titre indicatif uniquement ; ne constitue ni une offre, ni une invitation à investir, ni un conseil en investissement. Les chiffres exacts, l'identité du promoteur et les documents du projet sont communiqués aux investisseurs qualifiés après le parcours d'intégration et le KYC d'AfCEN, sous accord de confidentialité.