Brownfield gold processing expansion in Burkina FasoIllustratif
Minéraux stratégiques et ressources naturellesAFC-BFA-MIN-22867

Bombore Gold Project — Stage 2 Hard Rock Expansion

Burkina Faso · CentreStrategic minerals / gold mining and processing · Hard-rock sulphide gold processing (expansion of an existing oxide operation)

Expansion of an operating gold mine in central Burkina Faso: Stage 2 lifts hard-rock throughput to 5–5.5 Mtpa inside the existing footprint, taking output towards 220,000–250,000 oz of gold a year for a preliminary USD 90–95m.¹

Coût du projet
c. USD 95m
Stage 2, preliminary USD 90–95m, February 2025¹
Capacité
5.5 Million tonnes per annum
250,000 Ounces of gold per year/an (modélisation)
Calendrier
To board approval
Then a 14-month build

Justification

The mine has poured gold from its oxide plant since December 2022, and a fully funded Stage 1 hard-rock plant is forecast to lift 2026 output to 170,000–185,000 oz.¹ Stage 2 adds processing units within the same footprint to reach 220,000–250,000 oz a year.

Stage
Operating mine; Stage 1 fully funded July 2024
Scheme
Hard-rock CIL plant beside the oxide plant
Capacity
5–5.5 Mtpa hard-rock throughput after Stage 2
Reserves
c. 2.4 Moz Proven and Probable at 0.72 g/t²

Opportunité d'investissement

Structure de l'opération

Debt or strategic equity in Stage 2 of a producing gold mine; Stage 1 was fully funded in July 2024 with USD 105m of debt and equity.

Utilisation des fonds

Four CIL tanks, an oxygen plant, a ball mill, a thickener and a pebble crusher, added within the Stage 1 footprint.

Source des revenus

Gold sales into a deep, liquid global market.

Ce qui est recherché

Regional debt or strategic equity partners for Stage 2, once the residual funding need is confirmed under NDA.

Pourquoi le projet est bancable

Producing since 2022.

Oxide plant in commercial production since December 2022, delivered on schedule and under budget; 110,014 oz produced in FY2025.³

Proven financing record.

Stage 1 was financed with a USD 58m senior loan from a regional bank and USD 47m of strategic equity from a West African investor.

Low-risk scope.

Stage 2 adds processing units inside the Stage 1 footprint, with a 14-month construction period.¹

Studied resource.

An NI 43-101 expansion study (October 2023) defines 103.5 Mt of Proven and Probable Reserves at 0.72 g/t.²

Données et éléments probants · Stage 1 today vs with Stage 2

Stage 1 (2026)With Stage 2
Gold output170,000–185,000 oz forecast for 2026220,000–250,000 oz a year target
Hard-rock plant2.5 Mtpa5–5.5 Mtpa, same footprint
FundingFully funded, July 2024Preliminary USD 90–95m; need under review

Degré de maturité et calendrier du projet

  1. OriginationOperating mine
  2. FeasibilityStudy Oct 2023
  3. StructuringCurrent stage
  4. Financial closePost-diligence
  5. ConstructionTo follow

Principaux risques et mesures d'atténuation

Approval and funding need

Stage 2 awaits final board approval; the residual funding need is confirmed with the sponsor under NDA before any terms.

Construction

Units are added inside the Stage 1 footprint over a 14-month build, by a team that delivered the oxide plant on schedule and under budget.

Gold price

Revenue follows the gold price; output sells into a deep, liquid global market.

Conditions de l'opération

Instrument sought
Debt or strategic equity, subject to a confirmed Stage 2 funding need
Contract status
Stage 2 subject to final board approval (latest status, February 2026)
Technology
Hard-rock carbon-in-leach (CIL) plant alongside the existing oxide plant
Annual output
Up to 250,000 oz of gold a year after Stage 2
Development stage
Operating mine; Stage 1 fully funded; Stage 2 study complete
WAIIS pillar
Strategic Minerals & Natural Resources

Impact sur le développement

Economic

Gold export earnings and fiscal revenue for Burkina Faso, which holds a free-carried equity interest in the mine.

Regional capital

Stage 1 drew on a regional bank and a West African investor, deepening regional capital-market participation.

  1. Indicative, from the sponsor's stock-exchange disclosure of 23 February 2025; Stage 2 remains subject to final board approval. Final figures released under NDA.
  2. Bombore Phase II Expansion Study (NI 43-101), 11 October 2023: 103.5 Mt at 0.72 g/t for 2,403 koz Proven and Probable.
  3. Sponsor disclosures, as summarised in the project's pre-feasibility analysis (2026).
  4. Images à titre d'illustration.

L'inscription crée un compte investisseur. AfCEN finalise le parcours d'intégration et le KYC avant de communiquer toute information au-delà de cette page. Le teaser PDF reprend exactement le contenu de cet écran, et rien de plus.

À titre indicatif uniquement ; ne constitue ni une offre, ni une invitation à investir, ni un conseil en investissement. Les chiffres exacts, l'identité du promoteur et les documents du projet sont communiqués aux investisseurs qualifiés après le parcours d'intégration et le KYC d'AfCEN, sous accord de confidentialité.