Hydro generation asset in Sierra LeoneIllustratif
Commerce de l'énergie et croissance industrielleAFCEN-SL-008

Betmai Hydroelectric Project

Sierra Leone · NorthernPower · Generation

A 27 MW run-of-river hydro scheme on the Pampana River in Northern Sierra Leone, delivering 142.9 GWh a year of modelled output under an agreed 25-year PPA into a grid that meets less than half of national demand.

Coût du projet
c. USD 103m
All-in, incl. grid link and IDC¹
Capacité
27 MW
142.9 GWh/yr/an (modélisation)
Capital recherché
USD 40m
Equity sought
Instrument
Fonds propres
Base case 70% debt, 30% equity
Calendrier
To financial close
Then construction

Justification

Grid supply is about 140 MW against unconstrained demand of about 320 MW, rising to 485 MW by 2030, and only 36% of Sierra Leoneans have electricity.² Betmai adds renewable baseload from a natural 60 m waterfall, with no large storage dam.

Scheme
80 m gross head; 40 m³/s design flow
Units
4 Francis: 1 × 2.7 MW, 3 × 8.1 MW
Grid
28 km 66 kV line to Magburaka
Stage
Late-stage development, to financial close

Opportunité d'investissement

Structure de l'opération

Equity in a 27 MW run-of-river plant with an agreed 25-year PPA.

Utilisation des fonds

Weir and intake, power canal, three steel penstocks, powerhouse and the 28 km 66 kV line.

Source des revenus

Plant-gate sale at USD 125/MWh (USD 105 generation, USD 20 transmission), escalating 2% a year.

Ce qui est recherché

Equity investors to join the raise that takes the project to financial close.

Pourquoi le projet est bancable

Unmet demand.

Grid supply of about 140 MW against 320 MW of demand, rising to 485 MW by 2030.²

Contracted revenue.

25-year PPA agreed with a utility offtaker, modelled as take-or-pay at USD 125/MWh.

Partners.

Government of Sierra Leone as PPA counterparty; supply to the national grid and West Africa Power Pool.¹

Anchor investors and supporters.

Open: equity positions available ahead of financial close.

Données et éléments probants · Hydrology and yield

43 yr
Flow record, 1969–2011
1,750 km²
Catchment area
42 m³/s
Mean river flow
80 / 76 m
Gross / net head
142.9 GWh
Modelled annual yield

Degré de maturité et calendrier du projet

  1. OriginationLate-stage development
  2. FeasibilityStudy updated 2017
  3. StructuringCapital structure under review
  4. Financial closeCurrent stage
  5. ConstructionTo follow

Principaux risques et mesures d'atténuation

Hydrology

43-year flow record correlated to an on-site gauge; run-of-river design avoids reservoir risk.

Offtaker payment

Take-or-pay PPA with a sovereign counterparty; credit support terms in the Tier 2 data room.

Cost and schedule

Estimates are at 2017 prices; the updated cost breakdown is released under NDA.

Conditions de l'opération

Offtaker
Utility; sovereign counterparty
Contract status
PPA agreed; 25-year tenor
Tariff basis
USD 125/MWh at plant gate, +2% a year
E&S category
AfCEN screening; category to be confirmed
WAIIS pillar
Energy Trade & Industrial Growth

Impact sur le développement

Access

Only 36% of Sierra Leoneans have electricity; the national target is 78% by 2030.²

Climate

Supports lifting renewables from 46% to 52% of the energy mix by 2030.²

Regional integration

Planned supply to the national grid and the West Africa Power Pool.¹

  1. Indicative, from the feasibility study update (2017, 2017 prices); capital structure under review. Returns released under NDA.
  2. Government of Sierra Leone, National Energy Compact (Mission 300), 2025.
  3. Images à titre d'illustration.

L'inscription crée un compte investisseur. AfCEN finalise le parcours d'intégration et le KYC avant de communiquer toute information au-delà de cette page. Le teaser PDF reprend exactement le contenu de cet écran, et rien de plus.

À titre indicatif uniquement ; ne constitue ni une offre, ni une invitation à investir, ni un conseil en investissement. Les chiffres exacts, l'identité du promoteur et les documents du projet sont communiqués aux investisseurs qualifiés après le parcours d'intégration et le KYC d'AfCEN, sous accord de confidentialité.