Seafood processing and cold-chain infrastructure in coastal Sierra Leone.Illustrative
Agribusiness & Food SystemsJMAN-FSH-01

JMan Fisheries Terminal & Ice Production Facility

Sierra Leone · Western AreaFisheries & Seafood Infrastructure · Industrial Fishing, Processing & Cold Chain Logistics

An integrated plant at Kissy Dockyard, Freetown

Project cost
c. USD 22.18m
Hard cost and soft cost
Capacity
150 tonnes/day
50,000 tonnes/year/yr modelled
Capital sought
USD 22.2m
Debt and equity
Instrument
Senior debt
75% debt and 25% equity
Timeline
Financing and approvals
Then construction

Rationale

A zero-waste facility to shift the maritime economy

Jetty
Deep-water jetty of about 120 m for 20-30 vessels
Processing
150 TPD processing, 40 TPD blast freezing
Cold chain
500-ton cold storage warehouses and a 50 TPD ice plant
Support
Truck logistics terminal, administrative and welfare facilities

Investment opportunity

Transaction structure

Debt financing for a greenfield seafood processing, blast freezing and cold-chain logistics project with concession land under negotiation.

Use of funds

The money funds civil and marine infrastructure, two modern stern freezer trawlers, solar PV integration, site dredging and seabed clearance, plus soft costs including design, supervision, contingencies, interest during construction and working capital margin.

Revenue basis

Revenue is based on three streams: waterfront landing and docking fees, fish processing charges and packaged fish sales, and storage and ice production income.

The ask

The project seeks a 75% debt and 25% equity financing package for the total project cost.

Why it is bankable

Marine resources, Freetown port, advanced ice and cold-storage facility.

Data and evidence · Key evidence figures

22.18 USD Mn
Total project cost
150 TPD
Processing capacity
50 TPD
Ice plant
500 ton
Cold storage
27.76 %
Project IRR

Project readiness and timeline

  1. Design6Months
  2. Financing and approvals6Months
  3. Construction18Months; construction and hiring start in quarter 3
  4. Regulatory readinessOnly HACCP documentation is prepared.
  5. Outstanding informationESIA data is still awaited

Key risks and mitigants

Permitting risk

29 permits and clearances; almost all pending, and only HACCP documentation is prepared.

Information risk

ESIA data, implementation strategy and project layout are still awaited.

Forecast risk

Information Client-supplied data, not independently verified. Forecasts depend on assumptions that may not be realized.

Transaction terms

Total project cost
USD 22.18 Mn
Funding mix
75% debt / 25% equity
D/E
3.00
Term loan rate
10%
Repayment period
Sep-29 to Dec-36

Development impact

Livelihoods

Over 1,000,000 livelihoods; 11.3% Of the population earns a living from marine fisheries.

Food security

About 80% of people eat fish as their main animal protein.

Jobs

350At start; 500At full capacity.

Local recruitment

Local recruitment moves artisanal fishers into certified industrial roles.

  1. Government of Sierra Leone Ministry of Fisheries and Marine Resources, 2024, https://faolex.fao.org/docs/pdf/sie214133.pdf
  2. China International Development Cooperation Agency, 2026, http://en.cidca.gov.cn/2026-04/25/c_1186340.htm
  3. Government of Sierra Leone Ministry of Fisheries and Marine Resources, 2024, https://faolex.fao.org/docs/pdf/sie214133.pdf
  4. U.S. Department of State, 2026, https://www.state.gov/reports/2026-investment-climate-statements/sierra-leone
  5. Government of Sierra Leone Ministry of Fisheries and Marine Resources, 2024, https://faolex.fao.org/docs/pdf/sie214135.pdf
  6. Images are illustrative.

Registering creates an investor account. AfCEN completes onboarding and KYC before anything beyond this page is released — the teaser PDF carries exactly what is on this screen and nothing more.

Indicative only; not an offer, an invitation to invest, or investment advice. Exact figures, sponsor identity and project documents are released to qualified investors after AfCEN onboarding and KYC, under NDA.