Northern Corridor Transmission Line (225 kV)
Sierra Leone · Multi-regionEnergy · High-voltage transmission (225 kV)
A 225 kV northern transmission corridor, a national priority project with feasibility completed, that links to the CLSG regional line and ends at a new Newton substation, relieving the single 161 kV feed to Freetown. USD 100m sought as blended equity and debt.
Rationale
About 140 MW of grid supply meets unconstrained demand of about 320 MW, projected at 485 MW by 2030, and a single 161 kV line carries Bumbuna hydro and imports to Freetown.² The corridor relieves that bottleneck and closes a 225 kV ring joined to the CLSG regional line.
- Line
- 225 kV overhead, with optical ground wire
- Route
- Northern region to a new Newton substation
- Link
- Joins the 1,303 km CLSG 225 kV line³
- Stage
- Feasibility completed; in structuring
Investment opportunity
Transaction structure
Blended equity and debt for a 225 kV line under a 25-year utility contract, now in negotiation.
Use of funds
A 225 kV line across the Northern region to a new substation at Newton, with optical ground wire.
Revenue basis
Transmission contract with EDSA, the national distribution utility, as offtaker; 25-year tenor in negotiation.
The ask
USD 100m in blended equity and debt, alongside the initial funds already secured, to build the corridor.
Why it is bankable
Among the priority projects of Sierra Leone's Mission 300 Energy Compact, with feasibility completed and initial funds secured.²
With the MCC-funded southern corridor, it joins the CLSG 225 kV line and ends at Newton, forming a national ring.²
One single-circuit 161 kV line carries Bumbuna hydro and imports to Freetown and limits use of the CLSG interconnector.²
About 140 MW of grid supply meets demand of about 320 MW, projected at 485 MW by 2030; mining is the largest growth load.²
Data and evidence · Sierra Leone grid: today and the 2030 plan
| Today (2025) | With the northern and southern corridors | |
|---|---|---|
| Main feed to Freetown | One single-circuit 161 kV line | 225 kV ring joined to the CLSG line |
| Transmission network | 802 km | 1,235 km by 2030 |
| Electricity access | 36% of the population | 78% target by 2030 |
Project readiness and timeline
- OriginationGreenfield
- FeasibilityCompleted
- StructuringCurrent stage
- Financial closePost-diligence
- ConstructionTo follow
Key risks and mitigants
The 25-year utility contract is still in negotiation; the offtake term sheet is released under NDA.
Revenue depends on the national distribution utility; mining load and lower-cost supply strengthen its revenue base.²
Category A on AfCEN screening; E&S impact documentation is released in the Tier 2 data room.
Transaction terms
- Offtaker
- Utility: EDSA, the national distribution utility
- Contract status
- In negotiation; 25-year tenor
- Instrument sought
- Blended: equity and debt
- Technology
- 225 kV overhead transmission line with optical ground wire
- Location
- Northern Sierra Leone to Newton, Western Area; route under NDA
- Development stage
- Feasibility completed; in structuring
- E&S category
- Category A (AfCEN screening)
- WAIIS pillar
- Energy Trade & Industrial Growth
Development impact
Access
Supports the national goal of raising electricity access from 36% to 78% of the population by 2030.²
Lower cost
Evacuates lower-cost hydro and imports; the Compact expects supply costs to fall to USD 14–16 cents/kWh.²
Mining and industry
Reliable, low-emission grid power for mining, the largest growth load.²
Integration
CLSG imports are estimated to replace about 80% of the thermal generation Sierra Leone would otherwise need.⁴